We are now continuing to weld structural clips to the columns. This will tie the colums, beams, and walls together. It is neccesary for the seizmec retrofit. The chilled water pipes are being installed overhead. We will set and achor the pans, after the pans are ancored we wil installed the coils. There are two types of coils, the first type is the chilled water coil which provides cooling. The other style of coil is a re-heat, which uses existing warm air to be transfered into the air system. It is part of a grren system which re-uses conditioned air. the fitters now will install piping headers. These headers will tie all the coils into a loop system.